Wind power plant with the installed capacity of 30 MW, consisting of the following main components:
Wind turbines: Gamesa
Type: 2 MW G97
Number of wind turbines: 15
Rotor: 97 m
Tower: 90 m
Electrical network: Dry step-up transformer located in the nacelle
The underground electrical network with a voltage of 20 kV and a 20-110 kV substation
NBB Renewables provides the following services:
On-site visits
Technical due diligence
Turbine inspections The technical due diligence reviewed key aspects of the project, such as performance of the power plant, sustainability approach, review of existing studies and documentation, assessment of the existing situation of the WTG and BOP infrastructure, financial and economic feasibility (operational and maintenance cost estimates), environmental and social impact assessment.